Dear all,
I am new to Primavera. With all the manuals I am sort of still lost on what is the meant procedure to update status / progress of activities in Primavera and you can change several things and the tool will re-calculate the other (e.g. updating duration % complete will update remaining duration)
Is my understanding correct, that procedure looks like this
Step 1
Think of Data Date for which you are updating progress
Step 2
Start activity, if it is started and update the actual start date, if different from the planned start date
Step 3
Update % complete
Step 4
Unless activity is set to be Duration % complete, then update remaining duration (otherwise remaining duration would have been updated when you were updating % complete )
Step 5
If activity has finished, click the “Finished” tickbox and select the actual finish date, if applicable
Step 6
Do a schedule run with the data date, thought of in Step 1
Replies