Budgeted Units-Export to Excel and Import

3 replies [Last post]
Kannan CP
User offline. Last seen 48 weeks 1 day ago. Offline
Joined: 12 Jun 2008
Posts: 290
Groups: None

Hi All,

I was trying to modify the budgeted units, by exporting it to excel and import back the modified values. Resource and units are set for all activities.

The issue is that in the exported excel file the sheet for resource assignment(TASKRSRC) is having only the heading, no details of the acivity, dates, budgeted units etc (blank cells).

Is any settings to be changed to have it in the sheet.

Thanks

BR

Kannan

Replies

Zoltan Palffy
User offline. Last seen 1 week 2 days ago. Offline
Joined: 13 Jul 2009
Posts: 3090
Groups: None

glad I could help 

Kannan CP
User offline. Last seen 48 weeks 1 day ago. Offline
Joined: 12 Jun 2008
Posts: 290
Groups: None

Thanks Zoltan...

Zoltan Palffy
User offline. Last seen 1 week 2 days ago. Offline
Joined: 13 Jul 2009
Posts: 3090
Groups: None

make sure to modfy the export and select the budgeted units

also when exporting select resources and resource assignments

then whne importing only select resource assignments so that you do not duplicate the resource.