P6 Beginner Question - Can you delete same predecessor from multiple activities

Member for

16 years 3 months

within P6 you can only delete multiple predecessors from and activity but you can not delete the same predecessors from multiple activities.

You can do this with sdk and the associated spreadsheet.

EVERYTHING is based on the activity id not the predecessor id