Actual units & EV did not update!!

7 replies [Last post]
X Planner
User offline. Last seen 9 years 18 weeks ago. Offline
Joined: 17 Jun 2002
Posts: 78
Groups: None

Dear All, 

 

   After updating my program i found the earned value and the actual units for "some" activities equal to zero ( didnot update), 

so i had to fix it manually on excel and import on p6, i'm usining duration %.

Any idea what could be the reason? and how to fix?

Thanks.

Replies

Zoltan Palffy
User offline. Last seen 1 week 10 hours ago. Offline
Joined: 13 Jul 2009
Posts: 3090
Groups: None

no problem

X Planner
User offline. Last seen 9 years 18 weeks ago. Offline
Joined: 17 Jun 2002
Posts: 78
Groups: None

Thanks Zoltan

Zoltan Palffy
User offline. Last seen 1 week 10 hours ago. Offline
Joined: 13 Jul 2009
Posts: 3090
Groups: None

the reason is that you are using duration % complete NOT physcial % complete

X Planner
User offline. Last seen 9 years 18 weeks ago. Offline
Joined: 17 Jun 2002
Posts: 78
Groups: None

Thanx Zoltan, I just wanted to know why it doesn't show any values. (the explaination)

Zoltan Palffy
User offline. Last seen 1 week 10 hours ago. Offline
Joined: 13 Jul 2009
Posts: 3090
Groups: None

to do what  ?

Mehmet Akif İbrah...
User offline. Last seen 9 years 32 weeks ago. Offline
Joined: 14 Sep 2015
Posts: 5
Groups: None

Hi,

 

You can write your data in UDF coulomn, after you import P6. And then Use Global change. 

Zoltan Palffy
User offline. Last seen 1 week 10 hours ago. Offline
Joined: 13 Jul 2009
Posts: 3090
Groups: None

use physical % complete