P6 Access Rights

3 replies [Last post]
Tom Turnham
User offline. Last seen 2 years 42 weeks ago. Offline
Joined: 21 Aug 2013
Posts: 18
Groups: None

Hi everyone,

 

I've had a quick search but couldnt find anything. What are the different levels of access you can grant to a user? Basically My manager has asked me if its possible to restrict an account so the user can only edit % complete or remaining duration etc. without causing any damage (deleteing things etc.)

 

Are there set levels or is it a more customable thing?

 

Thanks for the help guys

 

Tom

Replies

Zoltan Palffy
User offline. Last seen 4 days 11 hours ago. Offline
Joined: 13 Jul 2009
Posts: 3090
Groups: None

once you create the profiles that you want you can assign specific rights for each of the profiles that you have created and choose which profile can create, assign,  or just view individual elements within that profile

Tom Turnham
User offline. Last seen 2 years 42 weeks ago. Offline
Joined: 21 Aug 2013
Posts: 18
Groups: None

Thanks for the reply!

 

Ive had a play with those and I can get a user account set up with certain priviledges but I think its a job for someone with a bit more knowledge in the matter than me

 

Thanks again

Murray Geddes
User offline. Last seen 5 years 3 weeks ago. Offline
Joined: 1 Mar 2004
Posts: 9

I haven't used them personally, but have a look at "Admin" > "Users" (set User name(s), passwords & profiles.

Also "Admin" > "Security Profiles" to set levels of access for each profile.

You should be able to add a restricted profile and then create a general User profile (eg "User" & no password) for people who want to go in to the programme and look/interogate it.

Hope that helps.