Right-click export to Excel -> other layout doesn't give any activities

4 replies [Last post]
Mi Mo
User offline. Last seen 6 years 13 weeks ago. Offline
Joined: 5 Mar 2019
Posts: 8
Groups: None

Hi everybody,

I have been searching for this everywhere, but no succes..

So I always had succes when I used the right-click -> export to excel option.

Now, I have saved some different layouts and when I use a different layout I get an Excel export without any activities.

It does show the title columns.

I tried different view-filters and by accident I had one activity already marked as 'in progress', now this one was shown in the dump.

 

Anyone any idea what the problem is?

Replies

Zoltan Palffy
User offline. Last seen 8 weeks 1 day ago. Offline
Joined: 13 Jul 2009
Posts: 3091
Groups: None

highlight them first then rigth click export to excel  

Santosh Bhat
User offline. Last seen 4 weeks 5 days ago. Offline
Joined: 15 Apr 2005
Posts: 381

Why are you right clicking? In your activity view, press CTRL+A to select all, then CTRL+C to copy to clipboard, then Past einto an Excel worksheet.

Mi Mo
User offline. Last seen 6 years 13 weeks ago. Offline
Joined: 5 Mar 2019
Posts: 8
Groups: None

I have DD+3D filter OR status 'in Progress'

It works to get the right view in P6, but when I export to Excel it doesn't give any results.

Mi Mo
User offline. Last seen 6 years 13 weeks ago. Offline
Joined: 5 Mar 2019
Posts: 8
Groups: None

Wait...

 

It doesn't have to do with the righ-click methode.. It doesn't export at all.

It is a 3 day lookahead filter, so I think it has someting to do with the date.