User defined field in projects window

1 reply [Last post]
Kevin Johnson
User offline. Last seen 9 years 49 weeks ago. Offline
Joined: 23 Oct 2013
Posts: 3

Hi

I've tried creating a user defined field for the projects window but for some reason after I've created it and then gone to put it into the layout it doesn't show as an option in adding columns. No problems with the other windows. Is there something within the settings that I need to change?

Thanks

Replies

Zoltan Palffy
User offline. Last seen 2 weeks 2 days ago. Offline
Joined: 13 Jul 2009
Posts: 3090
Groups: None

udfs will be at the botom when looking for them