Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Forecast curve preparation to Client

8 replies [Last post]
Kannan CP
User offline. Last seen 47 weeks 2 days ago. Offline
Joined: 12 Jun 2008
Posts: 290
Groups: None

Hi All,

In our Project, we have to prepare a forecast cost curve along with the monthly report. I am following the below procedure to make it in P6, with the settings"fixed durations and units" and "Physical Percent Complete"

After updating the schedule and getting the earned value cost for each activity, I copy & paste it to the actual cost column(manually & boring). In my knowledge, P6 will calculate the remaining cost of the project starting from the actual cost (not earned value cost).

I tried global change to make the actual cost similar to the EV cost, but didn't work.

I would like to know your experiences.

Thanks

Best Regards

Kannan

Replies

Kannan CP
User offline. Last seen 47 weeks 2 days ago. Offline
Joined: 12 Jun 2008
Posts: 290
Groups: None

I found the reason for the change, the Performance Factor(PF) to calculate ETC was not 1, but 0.88. Now the problem solved.

 

Regards

Kannan

Kannan CP
User offline. Last seen 47 weeks 2 days ago. Offline
Joined: 12 Jun 2008
Posts: 290
Groups: None

Hi Gary,

I tried the settings as you mentioned, unfortunately am not getting the required result. may be I am missing something.

 

For eg:

BAC=1500

Earned Value Cost=750 (activity 50% complete)

Actual cost=1071 (changing as per the remaining duration, I am not following it)

Estimate to Complete = 660 (as per the setting it should be 1500-750=750)

therefore Estimate at completion= AC+ETC=1071+660=1731

Am i missing any setting to get the correct ETC.

 

Thanks

Regards

Kannan

Kannan CP
User offline. Last seen 47 weeks 2 days ago. Offline
Joined: 12 Jun 2008
Posts: 290
Groups: None

Hi Raymund,

This curve is for the client, not for our internal. Client is not concerned about our internal actual cost and the expenses. The Client want from P6, the balance budget cost distribution as of a month end (Budget cost-Earned value cost).

As Gary informed , I am going to try those settings in P6.

Best Regards

Kannan

Kannan CP
User offline. Last seen 47 weeks 2 days ago. Offline
Joined: 12 Jun 2008
Posts: 290
Groups: None

Thanks a lot Gary....

 

Regards

Kannan

Kannan CP
User offline. Last seen 47 weeks 2 days ago. Offline
Joined: 12 Jun 2008
Posts: 290
Groups: None

Hi Mike,

I believe that this kind of trend curves based on the average of actuals can be prepared in the excel sheet. If it includes different types of activities, it may be time consuming as well (for eg: taking the actual productivity rate for pipe laying, cabling works, ceramic tiles installation etc) to deploy the future values of these activities in a single curve.

In my case the client is looking for the values directly from the P6(the remaining cost of the balance activities in the project). From the client point of view, the actual cost is Earned value(in my opinion its true because the client is paying us based on the earned value as of month end(ofcourse after discussion) and that is the actual cost for them as of that month end)

Regards

Kannan

Raymund de Laza
User offline. Last seen 27 weeks 5 days ago. Offline
Joined: 23 Nov 2009
Posts: 762

Kannan,

As I understand a Forecast Cost Curve is a Planned Value Curve. When updating a schedule the value you get will be Earned Value which is to be compared with your Planned Value from the Baseline. Both Values will also be compared with the Actual Cost/Expenses incurred.

 

Regards,

Gary Whitehead
User offline. Last seen 6 years 6 days ago. Offline

Kannan,

 

It sounds like you want P6 to give you a forecasted ETC (Estimate to Complete) cost, rather than a remaining cost.

 

Go to Admin>Admin Preferences>Earned Value tab. There are a number of options for calculating ETC, including the simple (Budget - EV), which I think is what you are after.

 

Cheers,

 

G

Mike Testro
User offline. Last seen 27 weeks 3 days ago. Offline
Joined: 14 Dec 2005
Posts: 4420

Hi Kannan

In excell you can project a forecast trend from actual previous data to forward time slots by compounding the average change from the actual to the future.

This will project a straight line - a more complcated formula will convert this into a projected curve by including the percentage change between previous time slots.

Best regards

Mike Testro