Resource Lag & resource multiplication

3 replies [Last post]
Essam Yassin
User offline. Last seen 7 years 9 weeks ago. Offline
Joined: 25 Dec 2013
Posts: 9
Groups: None

Hi, Every body 

How could i assign a resource with a certain lag for a particular activity ?

Then is there a way to make multiplications in resource assignment ( ex, to assign 3 workers for an activity , h repeat assignment trible which i believe it's ot practical ) ?

Thanks in advane

Replies

Dieter Wambach
User offline. Last seen 7 years 16 hours ago. Offline
Joined: 15 Jan 2007
Posts: 1350

Hi Essam

i don't know a multiplicator. You'll have to select twice , triple, ... The units are taken from the resource's default units

For a choice by profession, study the chapter of the role concept in your reference manual.

Regardss

Dieter

Essam Yassin
User offline. Last seen 7 years 9 weeks ago. Offline
Joined: 25 Dec 2013
Posts: 9
Groups: None

Thanks Wambach

The forst question ( Resource lag ) i got it yasterday

But for second one, i know that i can add whatever resource to an activity . My point is how to avoid clicking the same resource or role while assignment ? Specially that i add resources (Manpower ) by proffesion not by name ?

Dieter Wambach
User offline. Last seen 7 years 16 hours ago. Offline
Joined: 15 Jan 2007
Posts: 1350

Hi Essam

This is from the P6 Help:

Original Lag (in the resource tab)

The planned time lag between the activity's planned start date and the resource's planned start date on the activity. If the resource is planned to start work when the activity is planned to start, the planned lag is zero.

You can assign a resource as often as you need - if allowed under project --> tab resources.

 

Regards

Dieter