Hello,
I have an issue when I update my resources scheduled for resources with an Original lag. If my resource has a 11days lag (original lag column) and if my activity has only started since 5 days then my Actual Units should be 0 and I should have no Actual Start date. But when I update my schedule, P6 put an Actual start date and so Actual units.
I have the same issue when I update a resource who start to work at the beginning of an activity but finish her work before the end of the activity.
I precise that before the update all the columns seem to be correct (planned, actual, remaining, ...)
You'll find below some precisions about my selected options:
- Activity type: Level of effort activity
- Duration type: Fixed duration and Units/Time
- % complete type: Duration
- Fields Calculate costs from Units and Auto compute actuals are thicked
- In Project Window I have selected the following options: Link budget and at completion for not started activities; Reset remaining duration and units to original; When updating actual units or costs Substract actual from at completion; Recalculate actual units and costs when duration % complete changes; Link actual to date and actual this period units and costs.
Below a screenshot before the update (sorry but I'm working in French language):
Below a screenshot after the update:
Can you help me? I have tried to change some options but this wasn't successfull.
Thank you!
Julie