Non-Labor Resource Assignment in Columns in a Layout

2 replies [Last post]
Pranab Kumar Deb
User offline. Last seen 4 years 14 weeks ago. Offline
Joined: 23 Jan 2007
Posts: 291

Hello All,

I am using Primavera Project Management 6.1, I want to see Non-Labor Resource Assignment in Columns in a Layout.  I am trying with setting User Defined fields and setting them to the budgeted quantities through Global Change, However the data is not coming right, How do I do that?

Thanks

 

Pranab

Replies

Patricia Le Clainche
User offline. Last seen 10 years 44 weeks ago. Offline
Joined: 18 May 2007
Posts: 86
Groups: None

Dear all,

Did you try in Resources Assignments View ? It should be OK. You can filter for instance by Resource Type =Non Labor. You can add columns dealing with costs. On spreadsheet, you can select costs or units, per period (month, quarter...) or cumulative.

Regards.

Patricia

Pranab Kumar Deb
User offline. Last seen 4 years 14 weeks ago. Offline
Joined: 23 Jan 2007
Posts: 291

Hi Schedulers,

Can this not be done? Can we not have a layout with all resource assignment? Has someone designed such a layout?

Thanks,

Pranab