Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Non-Labor Resource Assignment in Columns in a Layout

2 replies [Last post]
Pranab Kumar Deb
User offline. Last seen 2 years 42 weeks ago. Offline
Joined: 23 Jan 2007
Posts: 291

Hello All,

I am using Primavera Project Management 6.1, I want to see Non-Labor Resource Assignment in Columns in a Layout.  I am trying with setting User Defined fields and setting them to the budgeted quantities through Global Change, However the data is not coming right, How do I do that?

Thanks

 

Pranab

Replies

Patricia Le Clainche
User offline. Last seen 9 years 21 weeks ago. Offline
Joined: 18 May 2007
Posts: 86
Groups: None

Dear all,

Did you try in Resources Assignments View ? It should be OK. You can filter for instance by Resource Type =Non Labor. You can add columns dealing with costs. On spreadsheet, you can select costs or units, per period (month, quarter...) or cumulative.

Regards.

Patricia

Pranab Kumar Deb
User offline. Last seen 2 years 42 weeks ago. Offline
Joined: 23 Jan 2007
Posts: 291

Hi Schedulers,

Can this not be done? Can we not have a layout with all resource assignment? Has someone designed such a layout?

Thanks,

Pranab