Hello All,
I am using Primavera Project Management 6.1, I want to see Non-Labor Resource Assignment in Columns in a Layout. I am trying with setting User Defined fields and setting them to the budgeted quantities through Global Change, However the data is not coming right, How do I do that?
Thanks