Gantt chart separation of activities

5 replies [Last post]
Tyler Woods
User offline. Last seen 11 years 27 weeks ago. Offline
Joined: 6 Nov 2012
Posts: 5
Groups: None

My project has several locations of work performed and I have them grouped by activity codes A,B,C... This does not appear to be enough separation for my customer.  Is there a way to insert a horizontal line to separate these activity groups?

Replies

Raymund de Laza
User offline. Last seen 43 weeks 22 hours ago. Offline
Joined: 23 Nov 2009
Posts: 762

Mike,

On bar options there is filter as critical or nomal. The same can be applied as location 1, location 2 and so on. Need to assgn the activities with those activity codes such as location 1, location 2 an so on... create bar legends as the activity codes and filter accordingly.

 

Regards,

muhammad anwar
User offline. Last seen 5 years 10 weeks ago. Offline
Joined: 5 Feb 2007
Posts: 46
Groups: TILOS

Mike,

Create a filter to pickup these bars

Then go to view - Bars and creat a new bar with desired color but in filter assign the created filter for those bars.

Regards

 

Muhammad

Mike Testro
User offline. Last seen 42 weeks 5 days ago. Offline
Joined: 14 Dec 2005
Posts: 4420

Hi Raymund

How do you put a different coloured bar on P6?

Best regards

Mike Testro

Gary Whitehead
User offline. Last seen 6 years 16 weeks ago. Offline

I don't think there's a way of creating a proper horizontal line, but you could insert a LOE activity at the top of each activity group, and give the bar a different colour.

Or increase the row height of the 1st activity for each group.

Raymund de Laza
User offline. Last seen 43 weeks 22 hours ago. Offline
Joined: 23 Nov 2009
Posts: 762
I suggests to create a different colored bar for each location.