Creating reports

1 reply [Last post]
Daniel Scott
User offline. Last seen 9 years 31 weeks ago. Offline
Joined: 6 Jan 2012
Posts: 2
Groups: None

Greetings all. I’m a new user of P6 rev7 and am having a challenge which I hope someone will help me with please. I would like to create a report to see resources man-hours, for a specific time period, of only the projects I have open. But, for some reason any report I create grabs all resources from any project within P6. I’m sure there is something simple I am missing. But for the life of me I can’t figure it out.

Regards,

 

Replies

Kaif Mohsin
User offline. Last seen 8 years 2 weeks ago. Offline
Joined: 15 Feb 2011
Posts: 44
Groups: GPC Qatar

Dear Mr. Daniel,

While creating the report through the 'Report Wizard' once you reach the 'Configure Selected Subject Areas' just create a new filter under the 'Filter' tab in order to show only the Manhours assigned to the open projects.

It should look like this:

Resource Type......................equals.....Labor

Assigned to Current Project....equals.....Yes

 

Best Regards,

Kaif Mohsin