Does anyone know how to define/create, (not alter the WBS element) new base methodologies for use with the project Architect.

i.e. say i wanted to replicate a project based upon a standard corporate WBS.

Replies

Jim Fairchild
User offline. Last seen 4 years 2 weeks ago. Offline
Joined: 17 Mar 2003
Posts: 10
You can create new base methodologies in Methodology Manager by exporting an existing project in P3e and then importing it into MM. When you import the project you are given a choice on whether to use Actuals or Planned values for the existing project.
This is actually quite neat because you have a chance to improve your methodologies after they have been used - continuous improvement.

Jim
Forum Guest
User offline. Last seen 7 years 15 weeks ago. Offline
Joined: 28 Jan 2009
Posts: 0
Groups: None
Project Architect is used to Import a Methodology from Methodology Manager into Project Manager.
You can either create a project through PA or import a Methodology into an exicting project.