How to default (FS) to start new activiy 1 day after finish date. ex. june 18 is finish date and the new actvity must start june 19. Thanks,
FS
Forum Sponsor
Top Posters
Dimitrios Theocharidis
3 posts
MichaelFuelsC
0 posts
anwar zeb
1 posts
olva seselima
1 posts
Muhammd Muneer
0 posts
sairam
0 posts
MARAT BILYALOV
0 posts
RichTea66
0 posts
Muneer Muhammad
1 posts
Manny Onifade
5 posts
you can also link them by the order you select them.
thanks a lot SANTOSH KUMAR PRASAD and Gary Whitehead, God bless
If you have a chain of these activities which must each be linked by FS with zero lag, you can highlight them all, right click, and choose "link activities"
It will link them in the order they appear on the screen
Link Activities