FS

4 replies [Last post]
Alain De leon
User offline. Last seen 9 years 9 weeks ago. Offline
Joined: 15 Jun 2012
Posts: 18
Groups: None

How to default (FS) to start new activiy 1 day after finish date. ex. june 18 is finish date and the new actvity must start june 19. Thanks, 

Replies

John Sims
User offline. Last seen 11 years 48 weeks ago. Offline
Joined: 2 Jun 2011
Posts: 49
Groups: None

you can also link them by the order you select them.

Alain De leon
User offline. Last seen 9 years 9 weeks ago. Offline
Joined: 15 Jun 2012
Posts: 18
Groups: None

thanks a lot SANTOSH KUMAR PRASAD and Gary Whitehead, God bless

Gary Whitehead
User offline. Last seen 6 years 14 weeks ago. Offline

If you have a chain of these activities which must each be linked by FS with zero lag, you can highlight them all, right click, and choose "link activities"

 

It will link them in the order they appear on the screen

SANTOSH KUMAR PRASAD
User offline. Last seen 8 years 32 weeks ago. Offline
Joined: 16 Aug 2010
Posts: 13

Link Activities