How to default (FS) to start new activiy 1 day after finish date. ex. june 18 is finish date and the new actvity must start june 19. Thanks, 

G
Gary Whitehead 👤 Member for 17 years 2 months

If you have a chain of these activities which must each be linked by FS with zero lag, you can highlight them all, right click, and choose "link activities"

 

It will link them in the order they appear on the screen