Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Projecting 20 per cent Delay in Ms project

3 replies [Last post]
Nagendra Aryal
User offline. Last seen 2 years 4 weeks ago. Offline
Joined: 1 Jul 2019
Posts: 6
Groups: None

Hi everyone, 

I have been asked to create a programme projeting 20% longer duration than original duration in Ms-project. I have to show finish date of all activities with longer duration in a new column. What would be the formula or any way to do this? Your help is much appriciated.

Thanks 

Aarya

Replies

Nagendra Aryal
User offline. Last seen 2 years 4 weeks ago. Offline
Joined: 1 Jul 2019
Posts: 6
Groups: None

Hi Alexandre,

That was the thing I was looking for. It did work perfectly. I really appriciate your help. Many thanks 

Nagendra 

Nagendra Aryal
User offline. Last seen 2 years 4 weeks ago. Offline
Joined: 1 Jul 2019
Posts: 6
Groups: None

Hi Alexandre,

That was the thing I was looking for. It did work perfectly. I really appriciate your help. Many thanks 

Nagendra