Activity Duration

3 replies [Last post]
Raf Many
User offline. Last seen 7 years 33 weeks ago. Offline
Joined: 2 Aug 2016
Posts: 6
Groups: None

Hi,

I have assigned manhours in the work column but the activity durations keep changing when I change the manhr value, how can I avoid changing activity duration?

Replies

Philip Day
User offline. Last seen 1 year 37 weeks ago. Offline
Joined: 25 Jul 2016
Posts: 16
Groups: None

Hi Raf,

 

There is an unbreakable link in Automatically Scheduled tasks. So if you change any of these parameters after you have initially created the Task, it will affect the others.

 

If you change the Task Type to: Manually Scheduled. Make the Required changes and then remember to change back to Automatically Scheduled, you should find that you were able to change just the field expected, without breaking anything else.

 

Did this solve your problem?

Kind regards,

Phil

Raf Many
User offline. Last seen 7 years 33 weeks ago. Offline
Joined: 2 Aug 2016
Posts: 6
Groups: None

Thanks

One more question;

when I change the activity duration the manhrs assigned change automatically, how can I avoid this?

Tom Boyle
User offline. Last seen 4 weeks 2 days ago. Offline
Joined: 28 Nov 2006
Posts: 304
Groups: None

Raf,

Change the Task type from Fixed Units (the default) to Fixed Duration.

Good luck, tom