Split bar

3 replies [Last post]
Kannan CP
User offline. Last seen 4 weeks 1 day ago. Offline
Joined: 12 Jun 2008
Posts: 290
Groups: None

Hi All,

After updating a MS Project Schedule, split bars are visible for the updated activities(i assume due to the logical links). How to avoid it and show a normal current bar for the full remaining duration.

 

Thanks

Best Regards

Kannan

Replies

Kannan CP
User offline. Last seen 4 weeks 1 day ago. Offline
Joined: 12 Jun 2008
Posts: 290
Groups: None

Thanks Tom.

Tom Boyle
User offline. Last seen 4 weeks 3 days ago. Offline
Joined: 28 Nov 2006
Posts: 304
Groups: None

Under "Scheduling options for this project:" in the File|Options|Schedule dialog, be sure that "Split in-progress tasks" is not checked, then you will get the behavior you want.

Note: I do not advise or recommend this approach, as you are basically conceding to the "progress override" condition.  i.e. you don't trust or understand your own schedule logic.  It's better to see where the out-of-sequence progress has occurred, then modify your relationships - if necessary - to reflect the current reality.

Tom Boyle
User offline. Last seen 4 weeks 3 days ago. Offline
Joined: 28 Nov 2006
Posts: 304
Groups: None

Under "Scheduling options for this project:" in the File|Options|Schedule dialog, be sure that "Split in-progress tasks" is not checked, then you will get the behavior you want.

Note: I do not advise or recommend this approach, as you are basically conceding to the "progress override" condition.  i.e. you don't trust or understand your own schedule logic.  It's better to see where the out-of-sequence progress has occurred, then modify your relationships - if necessary - to reflect the current reality.