How do you assign weight to the activities

1 reply [Last post]
Claudio Inocencio
User offline. Last seen 9 years 41 weeks ago. Offline
Joined: 3 Oct 2013
Posts: 3
Groups: None

Hi, i need to specify the weight (incidence, etc) of the activity. Using the resources....a mean work hours...

if i have:

 

Proyect Name            10 working hours (summarize)       % of working hours of total

- Act 1                      2 working hours                             20%

- Act 2                      2 wh                                            20%

- Act 3                      2 wh                                            20%

- Act 4                      4 wh                                            40%

 

how do you show this percent? .... do you have to create?? how do you create?? .... (sorry my english), hope you can helpme

 

Bye!

Replies

Mike Testro
User offline. Last seen 8 weeks 2 hours ago. Offline
Joined: 14 Dec 2005
Posts: 4418

Hi Claudio

Welcome to Planning Planet.

You will never have to apply weighting again if you set your programme at level 4 with each task representing one trade in one location.

Best regards

Mike Testro