As Late as Possible

1 reply [Last post]
Deepak Jain
User offline. Last seen 10 years 3 weeks ago. Offline
Joined: 14 Jan 2006
Posts: 31

While using ALAP constraint, Could someone please suggest how to change the setting to conduct dates calculation from Free slack variable instead of Total slack ?

Thnx in advance,

Dipak

Replies

Gary Whitehead
User offline. Last seen 4 years 42 weeks ago. Offline

Dipak,

 

I don't think you can, but if you discover otherwise please let me know. -This is one of my major gripes with MS Project.

 

Good luck!

 

Gary