How to see (explore) the source of linked field.

1 reply [Last post]
Evgeny Z.
User offline. Last seen 40 weeks 1 day ago. Offline
Joined: 13 Jan 2008
Posts: 442
Groups: None

 

I am just playing around with Linked fields in Ms project (Paste Special => Paste Link). This seems to be quite a powerful feature especially taking into account, that one can link both within file as well as even to outside file (e.g. even to Excel) .

However the big problem is that it seems to impossible to see where the field is linked to. One can see, that there is a linked field (little triangle and “Linked Fields” flag), but I found no way to see, where it is actually linked to

Any idea how I can see it?

Replies

Ron Beechey
User offline. Last seen 5 years 8 weeks ago. Offline
Joined: 13 Jun 2002
Posts: 61

Click on the show icon and it will show on your Gantt chart area with the title of the document or spread sheet