Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

How to link Percent Complete to Progress Periods

1 reply [Last post]
Cameron Illingworth
User offline. Last seen 2 years 20 weeks ago. Offline
Joined: 17 Feb 2021
Posts: 7
Groups: None

Good morning everyone,

I would like to link the Percent Complete to the Progress Period so that when I am looking at each Progress Period, the Percent Complete entered will reflect that Progress Period. This relationship is present with the Progress Period dropline, so that if I display ultiple Progress Period droplines, they reflect the percentages I entered for the period. But once I enter progress into Percent Complete, this value in the spreadsheet doesn't change when alternating between Progress Periods.

 

Is there anyway to do this?

 

Many thanks,

Cameron

Replies