Durations

2 replies [Last post]
Craig McDougall
User offline. Last seen 13 years 36 weeks ago. Offline
Joined: 4 Dec 2011
Posts: 3
Groups: None

 hi, I'm an undergrad Mechanical Engineer and I'm having a bit of trouble setting up the durations for a project I'm working on. I have the project starting on 05/12/11 and the first task has duration set to 84 days, however the task is showing as complete by 01/02/12 (61 days latter). I've been trying to sort this out for about an hour and I'm starting to go nuts.

 There are 20 tasks in the project with varying durations, none of which are displaying in the project window as lasting as long as they should The whole project should last a little over 4 years and its ending a little after 1, despite having 2 tasks that take over 1000 days.

I'd really appreciate some help with this.

 

Craig

Replies

Craig McDougall
User offline. Last seen 13 years 36 weeks ago. Offline
Joined: 4 Dec 2011
Posts: 3
Groups: None

 Hi Mike,

             sorry I took so long getting back her. You were right, everything pretty much went to plan afeter I got the calanders sorted out.

 

Craig

Mike Testro
User offline. Last seen 38 weeks 3 days ago. Offline
Joined: 14 Dec 2005
Posts: 4420

Hi Craig

Welcome to Planning Planet

With such a broad programme it is almost inevitable that the original estimated durations will have nothing to do with reality - so don't take them as correct.

Your problem is most likely calendar related.

Check that your duration column is formatted to working days if your calendar is set to working days.

Best regards

Mike Testro