Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Not transparent behavior of scheduler

1 reply [Last post]
Maciej G
User offline. Last seen 12 years 42 weeks ago. Offline
Joined: 1 Jul 2011
Posts: 2
Groups: None

 

I have set two tasks in automatic mode: one task after another using predecessors link as defined below. Task A is completed in 100%. 

Id |Task Name |Predecessors|Start|Finish
265|Task A|264|Fri 24/06/11|Mon 27/06/11
266|Task B|265|Fri 29/07/11|Thu 04/08/11

What I don't understand is why MS Project schedules Task B a month after the first one. I'm particularly missing feedback from MS Project justifying this decision. Without this feedback nailing down the problem and its reason becomes hard.

  1. What could be the possible reason for that?
  2. How can I get feedback from MS Project with explanation why the given task has been scheduled in a certain way?

Some more details here:

  1. Task B contrain type is "Start as soon as possible"
  2. Resources assigned to the task have no holidays in this period (no exceptions in calendar)

Thank you in advance,

Maciej

Replies

Mike Testro
User offline. Last seen 5 weeks 2 days ago. Offline
Joined: 14 Dec 2005
Posts: 4418

Hi Maciej

What was the date of your progress report where you set task A at 100%?

Best regards

Mike Testro