Duration in Hours not in days

2 replies [Last post]
Jhorbam Baena Orozco
User offline. Last seen 2 years 20 weeks ago. Offline
Joined: 14 Sep 2009
Posts: 75
Groups: None
Hi...how can i change the duration type of my project?..By default the project duration is in days...but i need to use hours...well...can someone to help me in this problem?

Thanks

Replies

Jhorbam Baena Orozco
User offline. Last seen 2 years 20 weeks ago. Offline
Joined: 14 Sep 2009
Posts: 75
Groups: None
Let me answer my question...Tools - Options - Programming and change tye type in show duration in ...

Ok...i made the traduction from spanish to english but i hope that seem like the english version.