Activity strech

2 replies [Last post]
assaf f
User offline. Last seen 10 years 2 weeks ago. Offline
Joined: 26 Dec 2007
Posts: 32
Groups: None
Hi,
How can I make activity A’s start & finish be dependant on two other activities? (B&C)
B will determine A’s start
C will determine A’s finish.
Both of them at the same time - I’ve tried SS & FF but only FF wound up determining A’s dates and SS had no infuence.

Thanks,
Assaf.

Replies

Trevor Rabey
User offline. Last seen 1 year 22 weeks ago. Offline
Joined: 29 Nov 2005
Posts: 530
Groups: None
Your question has already been answered at microsoft.public.project