Hi,
How can I make activity As start & finish be dependant on two other activities? (B&C)
B will determine As start
C will determine As finish.
Both of them at the same time - Ive tried SS & FF but only FF wound up determining As dates and SS had no infuence.
Thanks,
Assaf.
How can I make activity As start & finish be dependant on two other activities? (B&C)
B will determine As start
C will determine As finish.
Both of them at the same time - Ive tried SS & FF but only FF wound up determining As dates and SS had no infuence.
Thanks,
Assaf.