Critical Path / Critical Activities

4 replies [Last post]
Alex Logie
User offline. Last seen 15 years 47 weeks ago. Offline
Joined: 21 Jan 2008
Posts: 6
Hi Planners


I’m new to planning need help from experienced forum members.
A small Schedule I created consist 56 Activities, does not show critical path or critical activities.
I know something isn’t right there, but unable to figure out.

what are the check available to detect the fault?
can some one shed some light on this please



Cheers

Alex

Replies

Alex Logie
User offline. Last seen 15 years 47 weeks ago. Offline
Joined: 21 Jan 2008
Posts: 6

it worked!!

Thanks a lot for your valuable info


Alex
Trevor Rabey
User offline. Last seen 1 year 22 weeks ago. Offline
Joined: 29 Nov 2005
Posts: 530
Groups: None
Check the Schedule Table to see the ES, EF, LS, LF, free slack and total slack.

Run the Gantt Chart Wizard to format Critical Tasks red.

Check Tools, Options, calculation to see that Critical is defined as zero total slack.
L.E.N. Lewis
User offline. Last seen 2 years 1 week ago. Offline
Joined: 2 Aug 2007
Posts: 47
Groups: None
Tools | Options | Calculation-tab.
Put a check mark in the box "Calculate multiple critical paths"

View | Tracking Gantt

(I *so* miss NZ -- did the Milford, went as far north as 90 Mile Beach, would love to live in Napier.)