Effort driven

1 reply [Last post]
moutaz aldeib
User offline. Last seen 37 weeks 5 days ago. Offline
Joined: 31 Dec 2003
Posts: 278
Groups: None
Dear Planners,

the effort driven is defult, however by deleting from tools,options,schedule (new tasks are effort driven), will not delete effort driven from the activities.

Regards,

Moutaz

Replies

Alexandre Faulx-B...
User offline. Last seen 12 hours 1 min ago. Offline
Joined: 20 Jan 2003
Posts: 1310
yâ moutaz,
whatever you are doing in msp options, it is for the future only
for existing tasks, select all the tasks, click project, task information, advanced, then check out the "effort driven" box
bqa 3la kheir