Question: Combined resource usage

No replies
Marko Rooseno
User offline. Last seen 17 years 15 weeks ago. Offline
Joined: 13 Jul 2006
Posts: 8
Groups: None
Hi Planners..

It’s me again, with another question.. *OH NO!!! EVERYONE HIDE!!!*

LOL.. Yea, I’ve got issues.. I know..

Anyways, I’ve made this file in MSP and inserted sub-projects that’s linked to other files in my system. Basically my objective is to provide a snapshot of all projects running in the firm that I work in.

The problem is that the resources are broken up into the different subprojects. What I’m after is a cumulative usage of the resources for the whole subprojects. Is this possible and how would I be able to do it?

I’ve tried another way like instead of inserting subprojects, i used copy/paste from each individual projects. This gives me what I want in terms of the cumulative resource usage, but the file doesn’t automatically update itself like it does when I use subprojects.

Thanks Planners!
M