Tasks showing up as critical that are not

2 replies [Last post]
tim Rodriguez
User offline. Last seen 16 years 43 weeks ago. Offline
Joined: 24 Apr 2006
Posts: 4
We are trying to manage the critical path on a project and there are some tasks that the project manager does not want on critical path. The first task that we tried to get off of critcal path proved to be a problem. We removed the predecessors to the task and it remained critical. We removed the successors to the task and it remained critical. It is unconstrained, un-linked, stand alone, only 7 days long in a several month project, and still remains critical. And the total slack remains at 0 no matter what we do.
What am I doing wrong?

Replies

tim Rodriguez
User offline. Last seen 16 years 43 weeks ago. Offline
Joined: 24 Apr 2006
Posts: 4
Alexandre,
Thanks for your reply. In the interim time period between my original post and now.....I realized that when we converted the file from P3, some resource calendars came over as well. These calendars were driving activities critcal. So thanks again for the reply!