Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Actual Start and Finish dates

7 replies [Last post]
Forum Guest
User offline. Last seen 2 years 28 weeks ago. Offline
Joined: 28 Jan 2009
Posts: 1
Groups: None
When trying to input the actual start and finish dates for a task completed, it changes the planned start and finish dates.

Is there any way where I can input the actual start and finish dates without changing the plan start and finish dates?????

Any help is appreciated

Thanks

Replies

faisal afsar
User offline. Last seen 11 years 49 weeks ago. Offline
Joined: 13 Jun 2008
Posts: 55
Groups: None
I didnt meant that adding two new columns of actual start and actual finish will not change the original duration try doing it it wont change it
Sreejith Nair
User offline. Last seen 12 years 44 weeks ago. Offline
Joined: 28 Mar 2008
Posts: 63
Hi!
I dont think what Faisal suggested exactly solve the issue.
The questioner want to prominently show the planned start and finish dates.
In your method, when ever we enter a date in the ’Actual start’ ,for all associated activities, ’Start’ And ’Finish’ date changes !
That means one wont be able to see the originally planned start and finished dates in the programme anymore! Duration variance will display some value only after we enter Actual start & actual finish (Both)
The best solution MSP can offer for this is:
Step-01: As soon as the project plan (Baseline) is approved , save it as baseline : Tools > Tracking > Save baseline > Entire project

Step-02: Right click on the ’Gantt chart’ area , select "Gantt Chart Wizard". In the wizard step02 , select ’Baseline’ view and proceed for formatting.

Step-03: Add two more columns :Insert > Columns
"Baseline Start" & "Baseline Finish"

Step-04 : Periodically update "Start" & "Finish| columns.
Change activity links as ’Performed’

Now what ever you do with start & finish dates / links , your original plan lays undisturbed in the backdrop as ’Baseline’ So anytime you can have a visual comparison of what was planned and what happened in real.

You may change the colour of baseline plan to some thing contrasting from the "actual" bar colour (In bar styles)

Hope this helps ..

Cheers

Sreejith Nair
faisal afsar
User offline. Last seen 11 years 49 weeks ago. Offline
Joined: 13 Jun 2008
Posts: 55
Groups: None
there is a simple answer to this simple question
go to insert/column/select the ID "actual start" and "actual finsih". two new columns will be inserted u can now feed in yor actual start and actual finish dates in these columns feeding these will also give you the days variance by again going the insert / column and selecting the ID Duration variance. this is how it is
Nicolas Igersheim
User offline. Last seen 7 years 16 weeks ago. Offline
Joined: 25 Jun 2007
Posts: 62
Gentlemen,

Searching for exactly the solution to this problem,
I came upon this thread.
It shows the search engine is accurate but,
when I tried to implement Raj’s solution,
I found that updating actual start still
moves the "current" start.
Of course I could modify the bars to show
Start1 and End1 instead of Start and End
but this would be a pain

Any suggestions

Thanks in advance.
Raj Maurya
User offline. Last seen 2 years 42 weeks ago. Offline
Joined: 17 Jul 2004
Posts: 132
Save as baseline is an option. But If you want to keep your current start & current finish unchanged after updating then copy all start & finish date in the field start1 & finish1. Then you can update the actual start & finish date.
Forum Guest
User offline. Last seen 2 years 28 weeks ago. Offline
Joined: 28 Jan 2009
Posts: 1
Groups: None
Hello,
You MUST enter the actual start end finish dates in the ACTUAL START / FINISH fields, not the (current) START / FINISH fields.
Before you entetr the 1st actual data, go to Tools, OPtions, Tracking and Save the baseline of your project.
ACTUAL dates will not modify / update the part of the planning already completed; if the actual does not comply with the planned, the still to be done part of the project will be updated.
Alexandre Faulx-Briole
http://perso.wanadoo.fr/afaulxbriole