Give Column Showing Original No. of Days Allocated

1 reply [Last post]
IT Student
User offline. Last seen 20 years 27 weeks ago. Offline
Joined: 13 Oct 2003
Posts: 14
Groups: None
Hi,

When you set a baseline for a task & then insert a Tracking GANTT, the "Duration" column updates to reflect the actual no. of

days taken. I need to have a column which shows the initially allocated no. of days. How can I do that?

TIA,

IT Student.

Replies

Will Russell
User offline. Last seen 11 years 12 weeks ago. Offline
Joined: 9 Apr 2003
Posts: 48
Groups: None
If you have set a baseline then the information you want is in the Baseline Duration column. Just insert that column into the Tracking Gantt view.
You really should go on an introductory course!!

Will