Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Claims for Design and Approval Issues

5 replies [Last post]
Dimple Dean
User offline. Last seen 7 years 46 weeks ago. Offline
Joined: 20 Oct 2015
Posts: 18
Groups: None

Hi All!

We are trying to prepare a claim for Design Issues. Our Project is a government project wherein we as a Consultant are preparing the Infrastructure Design and submit to the Government for Approval.
Below Details is our scenario.

StartFinishActivity
3/8/201315/2/2014Design & Approvals Planned & Finish Date
10/10/201331/7/2014on 10-10-13, we submitted the original design and approved by them on 31-7-14
14/4/2013 a letter sent to Government from Company A (Gov't Infra Consultant) informing the Gov't to change Infrastructure sewer design connection
31/7/2014 Original Design Approved by Government
20/8/2014 on this date, we just receive the letter dated 14 April 2013, which is too late since the original design was already approved on 31 July 2014
31/10/2014 Withdrawal of Original Design by Consultant
8/11/2014 Instruction from Government to Us (Consultant) to proceed with revised design
20/3/2015 Redesign Approved by Government 

Contractual Start of Infrastruction Works was 30 July 2014.
Because of the design changes, we are trying to prepare a claim against the Government using Impacted as Planned. My question is how can I prepare a claim or substantiate my claim?
I find it hard to analyze the above situation. To all experienced and experts thanks in advance.
 

Replies

Dimple Dean
User offline. Last seen 7 years 46 weeks ago. Offline
Joined: 20 Oct 2015
Posts: 18
Groups: None

thanks very much Mr. Mike and Hemant.

We are claiming both time and cost associated with the design changes.
The information you have provided is very informative.

Mike Testro
User offline. Last seen 25 weeks 5 hours ago. Offline
Joined: 14 Dec 2005
Posts: 4420

Hi Dimple

20th March 2015

Best regards

Mike Testro

Hemant Bharat
User offline. Last seen 8 years 12 weeks ago. Offline
Joined: 12 Nov 2010
Posts: 8
Groups: None

Few more questions, what do you want to claim? I see two components, 1. Additional costs of design only and 2. Overhead and Profits or 3. both items 1 and 2?. the first step is to seperate direct design costs and overheads. 

There are some missing information and if i have got anything wrong please provide the same. 

1. Additionals Costs

You had already done a design once, from 03/08/2013 to 10/10/2013, a period of 68 days. It had been submitted and approved (approved part not important as long as you have done the design to the required brief). 

Your second design is from 8/11/2014 to 07/01/2015 (a period of 60 calender days). this is your additional direct design costs. 

2. Overhead costs

Instead of the initial  approval planned date of 15/2/2014 your design has been approved on the 31/7/2014. This is 168 calender days and you are entitled for the overhead costs for keeping the project live in the consultants books for this period which requires someone's attention. 

You could also claim for, keeping this project live from 20/8/2014 to 20/3/2015. 

It would be prudent to talk to your seniors to understand what they want to claim for, as it is also dependent upon your relationship with the client.  

Dimple Dean
User offline. Last seen 7 years 46 weeks ago. Offline
Joined: 20 Oct 2015
Posts: 18
Groups: None

Mr. Mike,

We submitted revised plans on 7 January 2015.
If the original start date of the original design approval was 10 October 2013, what is the date for late design approval?

Kind Regards,

Dimple

Mike Testro
User offline. Last seen 25 weeks 5 hours ago. Offline
Joined: 14 Dec 2005
Posts: 4420

Hi Dimple

This does not need a full Impacted as Planned analysis.

You just shift the original start date of the original design approval to the late design approval.

You may have a problem between 8-Nov-14 when you were instructed to change and 20-Mar-15 when you got the approval.

There is at least one date missing - When did you submit the revised plans?

Best regards

Mike Testro