Hi All!
We are trying to prepare a claim for Design Issues. Our Project is a government project wherein we as a Consultant are preparing the Infrastructure Design and submit to the Government for Approval.
Below Details is our scenario.
Start | Finish | Activity |
3/8/2013 | 15/2/2014 | Design & Approvals Planned & Finish Date |
10/10/2013 | 31/7/2014 | on 10-10-13, we submitted the original design and approved by them on 31-7-14 |
14/4/2013 | | a letter sent to Government from Company A (Gov't Infra Consultant) informing the Gov't to change Infrastructure sewer design connection |
31/7/2014 | | Original Design Approved by Government |
20/8/2014 | | on this date, we just receive the letter dated 14 April 2013, which is too late since the original design was already approved on 31 July 2014 |
31/10/2014 | | Withdrawal of Original Design by Consultant |
8/11/2014 | | Instruction from Government to Us (Consultant) to proceed with revised design |
20/3/2015 | | Redesign Approved by Government |
Contractual Start of Infrastruction Works was 30 July 2014.
Because of the design changes, we are trying to prepare a claim against the Government using Impacted as Planned. My question is how can I prepare a claim or substantiate my claim?
I find it hard to analyze the above situation. To all experienced and experts thanks in advance.
Replies