Guys,
Got int a debate yesterday with some colleagues on the topic of Progress overide or retained Logic. when carrying out a delay analysis, Time impact for example, should the analyst use retained logic or progress overrride?
Thanks in advance
Guys,
Got int a debate yesterday with some colleagues on the topic of Progress overide or retained Logic. when carrying out a delay analysis, Time impact for example, should the analyst use retained logic or progress overrride?
Thanks in advance
I believe the correct way is to initially use progress over-ride, but check that the current logic is still correct.
I know that in all of Mike T's programmes on F-S relationships are used so if the following occurs
Concrete first floor F-S Walls First to 2nd - Planned sequence
Walls First to 2nd start prior to completion of first floor concrete Actual , and no walls to 2nd are in the area of incomplete 1st floor then progress override is correct. If some of the walls sit on the incomplete area of slab then retained logic should be used, or the relationship between 1st floor and walls changed to F-F.
Hi John
My problem with the AACE protocol is that it is difficult to understand what is behind the garbled text.
I have considerable concerns that the new Guild document on EoT will be similarly arcane.
The starting point in any delay analysis is the original programme that was set up at the beginning of the project which demonstrates the contractor's original intention.
A delay analyst that tampers with the logic is either brave or stupid.
It is reasonable to remove or adjust obvious flaws in the programme before starting the analysis but any time over runs that result from the adjustments are to the contractor's account.
I recall getting a baseline programme that was used for a delay analysis for a sports hall where there was an acclimatisation period for the sprung floor - set as an activity - which was on the critical path.
When I changed the calendar on the task from a 40 hour week to 24/7 the eoT claim collapsed.
Best regards
Mike Testro
from AACEI - 49R-06