Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Contractor variations

22 replies [Last post]
Gary Whitehead
User offline. Last seen 6 years 1 week ago. Offline
Here’s the situation:

A concept design forming part of a contract issued by client proved to be unfeasible when the contractor went out to tender with suppliers of the relevant equipment.

A period of time was spent investigating alternative solutions. (critical path)

The equipment suppliers proposed an alternative solution which was accepted by the client.

The equipment required for this solution was subject to significantly reduced delivery lead times. (critical path)

The net impact on project completion was virtually zero.

Under the contract, any contractor proposed variations which are accepted by the client do not change target completion date.

Here’s the question: Can the contractor treat the work to find an alternative solution as a seperate EOT (time, not cost) claim, and treat the gains in procurement time as a contractor proposal which has no impact on the contract completion date, or should the two be assesed together as a (virtually) nil change to contract completion?


I’m struggling to get hold of the contract docs on this one, so appreciate any answers given will be subject to the specific wording in the relevant clauses.


Thanks in advance,

G

Replies

Samer Zawaydeh
User offline. Last seen 6 years 14 weeks ago. Offline
Joined: 3 Aug 2008
Posts: 1664
Dear Gary,

Adding to Trevor point, the Conditions of Contract are a good guess using the industry standards and best practices to have a formal document between two parties. It can’t be totally proof against all events.

I used to keep with me an A4 paper with about 4-5 lines. This was the agreement between an investor and an engineer during the 50’s when they started a Construction company that became huge in the region until our present day based on the trust between the two parties.

With kind regards,

Samer
Trevor Rabey
User offline. Last seen 2 years 28 weeks ago. Offline
Joined: 29 Nov 2005
Posts: 530
Groups: None
Hey Gary,

Call me naive, but I would have thought that when two parties enter into a contract they do so in good faith, and write it all down so that they both know what the agreement is. I thought it was an agreement, not a weapon.

If the client thinks that the contract is written in such a loose way that it exposes them to the risk that the contractor can find holes big enough to drive a truck through, and will try it, then shouldn’t they just re-write it "better" until they are more comfortable, or at least not sign it?

If your client decides to be more adversarial, isn’t that just an invitation to the contractor to take the gloves off and go in hard as well? How does escalating the aggravation help anyone?

If the contractor proposal is rejected, then it is rejected. Later when it comes from the client, they can squeal as much as they like that they thought of it first, but that is irrelevant. If he re-submits it again the client can reject it again. Why? Because they can.

Yes, I know we should read the contract to see what has been agreed.
Samer Zawaydeh
User offline. Last seen 6 years 14 weeks ago. Offline
Joined: 3 Aug 2008
Posts: 1664
Dear Gary,

Since the situation is hypothetical, you can asnwer your client that in case the Contractor decides to waste time in sending too much paperwork, then you will hire someone to answer all of these issues and at the end of the Contract, if these issue make a patter that is obvious, you can submit a claim stating that the Contractor is delaying the works and let them pay for the entire services.

The clauses in international contracts are set up to be balanced. And they were written with that intention in mind. If someone wants to override these, I am sure that you can find another close to balance its effect.

With kind regards,

Samer
Gary Whitehead
User offline. Last seen 6 years 1 week ago. Offline
Hi Trevor,

One of the contractors we’ll be working with has tried something similar (not a pre-emptive variation, but claiming a variation was contractor proposal when it wasn’t, semmingly just because good minutes weren’t available to disprove it) on a previous project.
Before my time so I don’t know the full details, but this is the reason the risk has been raised.
Also my client is moving towards a more adversarial form of contract administration than it has used in the past, so is expecting contractors to hit back.

Presumably if the client rejects the contractors proposal, and then 6 months later issues the very same under a client variation, the contractor would then point out this was his idea all along and resubmit the contractors variation.

I totally disagree that reading the contract is evidence of complete failure. It’s pretty fundamental to good project management & control, IMHO.

Maybe we are worrying about nothing, but my client is concerned and I said I’d ask around.
Trevor Rabey
User offline. Last seen 2 years 28 weeks ago. Offline
Joined: 29 Nov 2005
Posts: 530
Groups: None
It’s a bit of a stretch into the deep hypothetical, isn’t it?
If it is a great idea, has any contractor ever tried it?
It has to be attempted before it ever gets to a court to be tested, and then there has to be some sort of a dispute arising out of it. Maybe it has been attempted many times and got away with. Or maybe no one has yet had the necessary unmitigated gall.

What is to stop the client, who is perhaps no fool and can see what is going on, from just rejecting the contractor’s variation proposal? This would be on the general principle that if there is going to be variations it is better to be the party dishing them out rather than being the party on the receiving end.

Almost all clauses in contracts have the potential for bizarre interpretations and unintended consequences. Most of the time it doesn’t happen. Looking for holes in the contract that can be ruthlessly exploited simply because the clauses aren’t perfectly written is hardly likely to foster good, cooperative relations. Actually having to read the contract is usually a good indicator that the relationship has been doomed for a long time. It’s evidence of complete failure.
Gary Whitehead
User offline. Last seen 6 years 1 week ago. Offline
Thanks again for everybody’s comments on this.

I now have a different, but relevant question, which is:
What is a Contractor’s Proposal?

To summarise the issue, if a contracor proposes a variation to the contract, which is accepted by the client, the target cost and contract durations cannot be reduced because of it.

So what is to stop a Contractor submitting hundreds of proposals on day 1 of the contract to cover any possible future variations which the client may issue, to ensure they see the benefit rather than the client?

The relevant contract (modified IChemE Burgundy) clause is:

17.1 The Contractor may at any time during the performance of the Contract submit a proposal for a Variation to the Project Manager. Initially such proposal should be given as a brief written outline as soon as the Contractor is first aware of the possibility of the Variation.

More specifically:
On a number of process upgrade projects I’m currently client rep for, a common constraint written into the contract will be to limit the contractor to take only 1 process unit out of service at any one time, to ensure the works continue to operate satisfactorarily.
The risk is that the contractor on day 1 will submit contractor proposals to work on more than one process unit at a time, knowing that should the project be delayed in the future then this would be a likely avenue the client would look into to recover delay.
All the process analysis & risk mitigation measures which would be required to allow more than 1 process unit to be out of service at a time, would be done by the client.
In such circumstances, it does not seem right that the contractor should see the benefit of such variations for doing nothing more than writing a couple of sentences at the start of the project, but this seems to be how the clause is written.
Does anyone know if such an issue has been tested in (UK) court?

Cheers,

G
Mike Testro
User offline. Last seen 27 weeks 6 days ago. Offline
Joined: 14 Dec 2005
Posts: 4420
Hi Samer

That is usually the case unless the Contract allows otherwise.

In most cases the full impact of an EoT can be reduced if the case includes omissions.

Best regards

Mike Testro
Samer Zawaydeh
User offline. Last seen 6 years 14 weeks ago. Offline
Joined: 3 Aug 2008
Posts: 1664
Dear Mike,

I do not think that it is allowed to reduce the Contract time because that is a Contractural Constraint. That is, even if the scope is reduced, the original time of the Contract still holds.

With kind regards,

Samer
Mike Testro
User offline. Last seen 27 weeks 6 days ago. Offline
Joined: 14 Dec 2005
Posts: 4420
Hi Mai

It is very rarely that an impacted delay event will give a negative result - unless it is by way of ommission - in which case the completion date should not be adjusted unless the ommission is part of a multi event analysis.

Best regards

Mike Testro.
Mai Tawfeq
User offline. Last seen 10 years 16 weeks ago. Offline
Joined: 4 Mar 2010
Posts: 96
Hi Guys:

I would like to add my input :

It seems to me one event only and the claim should be assessed as one .
Usually any event has an echo and such echo can touch 1 to 100 activities in the program.
Any changing in the specification could be a good reason to claim weather negative or positive.
Anyway if the main contractor submit the work program and approved by the consultant considering the client benefits and the program has some / few activities related to our event so the contractor duty to apply the changes in such and see the impact how will come (-/+).
And in case there is no approved base line u have full right to reject till the contractor can prepared a high professional scenario and make to parties decision makers agree in principle to give him a time variation .

Thanks mai
Samer Zawaydeh
User offline. Last seen 6 years 14 weeks ago. Offline
Joined: 3 Aug 2008
Posts: 1664
Dear Gary,

Please keep in mind that the software gives the "what if" analysis scenarios according to the input given to the software.

What you have is continuous hands on the situation. This is also very much valuable.

Since you have an ongoing issue, I would highly recommend that the Work Management Control Records be very specific about the events that are taking place on a daily basis.

With kind regards,

Samer
Samer Zawaydeh
User offline. Last seen 6 years 14 weeks ago. Offline
Joined: 3 Aug 2008
Posts: 1664
Dear Mike,

I agree with you 100%, but Gary has the "determination" power. The Contractor must submit enough evidence to convience him that the EOT is justifiable. If Gary can’t determine, then that means the information made until now is not complete.

With kind regards,

Samer
Gary Whitehead
User offline. Last seen 6 years 1 week ago. Offline
Thanks for the input, gents.

I’ve decided to reject the claim on the basis that it is a single event with no overall time impact. We’ll see how they respond.

A bit of a mute point now as I have just found out there is another client delay which will probably result in a greater EOT that the contractor was looking for anyway.

Thanks again,

Gary
Mike Testro
User offline. Last seen 27 weeks 6 days ago. Offline
Joined: 14 Dec 2005
Posts: 4420
Hi Samer

What Gary wants is irrelevant - what is written in the contract applies.

Best regards

Mike Testro
Samer Zawaydeh
User offline. Last seen 6 years 14 weeks ago. Offline
Joined: 3 Aug 2008
Posts: 1664
Dear Mike,

The issue here is that Gary does not want to give them time. The new kit saved time, and the extra time needed for the change in design = time saved in using the new kit.

Either the Contractor submits a better EOT claim, or Gary can reject it.

With kind regards,

Samer
Mike Testro
User offline. Last seen 27 weeks 6 days ago. Offline
Joined: 14 Dec 2005
Posts: 4420
Hi Gary

Having read your first thread again it would seem that problem and the solution revolve around the one event.

The original kit would not work and the proposed piece of kit does work and the change can be made within the same time frame.

I can see where the Contractor is coming from whereby the Employers error causes a delay but the contractor’s solution does not reduce it.

Was there any obligation on the Contractor to check the viability of the original spec?

If not there may be some negotiation routes:

1. Offer time but no money.
2. Agree to allow the time against a future Contractor’s delay - a sort of time risk buffer.

Best regards

Mike Testro
Gary Whitehead
User offline. Last seen 6 years 1 week ago. Offline
Hi Mike,

I agree with the principal, but the alternate solution proposed which saves the time was a change to the contract spec, hence contractor is arguing that he was not obliged or even allowed to do this without a variation, and he performed his mitigating duties by identifying an alternate solution via a contractor’s variation to the spec.
And the contract is reasonably clear that contractor variations cannot be used to reduce contract price or bring contract completion forward.

Cheers,

G
Mike Testro
User offline. Last seen 27 weeks 6 days ago. Offline
Joined: 14 Dec 2005
Posts: 4420
Hi Gary

Whatever the cause of the delay the Contractor is obliged to mitigate any delay provided it does not cost any money.

So even if it is treated as two causes the net result should be 0 EoT.

Best regards

Mike Testro
Samer Zawaydeh
User offline. Last seen 6 years 14 weeks ago. Offline
Joined: 3 Aug 2008
Posts: 1664
Dear Gary,

It depends on what they submitted in their Progam of Works after award and Commencement of works and what you approved at the start of the Contract.

Usually,you have 5 sections in each Schedule:

Material Submittals,
Shop Drawings Submittals
Material Procurement
Construction
Commissioning

In this case, you have a variation; an added activity which took time to produce a new design. You have two tasks: a) Planning: you know what actually happened and when it happened b) Scheduling:to study the impact on the Critical Path.

It seems that the Contractor’s claim is not complete. Hence, you are having doubts in assessing the claim. You can send them back to the drawing boards again and ask for better presentation.

Actually the Contractor can proceed with making 5 different claims if they wish. It all relates to one issue.
The Scheduling issue here is to study the impact of the new design. They have to try harder to convince you logically that this is what was supposed to do, and what they did. Not an easy task at all.

You are corect, the Contract Durtion will not change if the work was reduced. That is a Contractual Constraint.

With kind regards,

Samer
Gary Whitehead
User offline. Last seen 6 years 1 week ago. Offline
Thanks for your reply, Samer.

I am actually representing the client.

To clarify the situation, the client had specified in the contract provision of X no. of Y-type equipment. When contractor went out to tender, suppliers informed that this would not achieve a sound engineering solution.

The client accepts responsibility for this error and agrees a variation is required.

The issue is that the contractor sees this as 2 variations:

Variation 1: EOT due to increased design time to find an acceptable alternate engineering solution
Variation 2: Implementing this alternative solution, which also came with a significant time saving on delivery periods. But these time savings cannot be translated into a ’negative EOT’ under the contract.

Hence they think they are entitled to a signficant EOT.

I think the two variations should be treated as one, and as such the delay in design would be balanced by the saving in delivery periods.
Samer Zawaydeh
User offline. Last seen 6 years 14 weeks ago. Offline
Joined: 3 Aug 2008
Posts: 1664
Dear Gary,

Maybe the following site will provide you with more insight and information:

http://www.ogc.gov.uk/procurement_documents_best_practice_guidance_.asp

With kind regards,

Samer
Samer Zawaydeh
User offline. Last seen 6 years 14 weeks ago. Offline
Joined: 3 Aug 2008
Posts: 1664
Dear Gary,

The start of the argument puts the Contractor in a weak position (I am assuming that you are representing the Contractor).

When the Contractor took the job, he SHOULD HAVE studied the job well and asked the pertinent suppliers at the time of tendering, or asked the Designer for specific details. I assume that the Condition of Contract that you are using is covering this issue.

If is obvious that EXTRA work has been done. And you are trying to get EXTRA Time for it.

EOT are studied and decided using Schedules, Critical Paths and near critical activities. This is depends on how much documents you have and how well you prepare your impacted schedule.

I hope that you mean by "alternative solution" an impacted schedule that will provide you with the same End Date.

If your original schedule is clear, maybe you can separate the event of arrival at site of the design equipment and the Construction and commissioning of it, and substitute it with the new one.

Do you like to discuss the actual effect of changing the design. I think that if you can identify EXTRA requirements that the Client made during the Change or Equipment process, maybe you can ask for EXTRA time.

With kind regards,

Samer