Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

smm7 help

1 reply [Last post]
Michael Cat
User offline. Last seen 15 years 51 weeks ago. Offline
Joined: 8 May 2008
Posts: 3
Groups: None
Hi,
Apoligies if this is not situtated in the correct forum, I was just wondering if any one could help me with a few questions in regards to smm7

why are types of finishes such as the staircase area,plant room and ceilings and beams over 3.50m measured seperately?

how are the different types of fittings in sturctural framing measured


When should working space allowance be measured in relation to a brickwall on a concrete strip foundation?

Replies

Anoon Iimos
User offline. Last seen 2 years 15 weeks ago. Offline
Joined: 22 Sep 2006
Posts: 1422
use a lot of common sense, works that are difficult to install or worked-out have higher rates