Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

delay analysis

2 replies [Last post]
pari alagan
User offline. Last seen 15 years 43 weeks ago. Offline
Joined: 11 Oct 2006
Posts: 4
Groups: None
hi,
In delay anlysis methods which is widley accepted and suitable for projects of value 100 million USD.And how primavera p3 can be helpful in delay analysis.pls can anyone briefly explain the analysis.

Replies

X Planner
User offline. Last seen 8 years 19 weeks ago. Offline
Joined: 17 Jun 2002
Posts: 78
Groups: None
yes, you have to go back to your contract what does it read on the method of assesment ,

if you are interested in time impact analysis,

u have to use your updated schedule for a certain month and to apply the delays one by one to calculate the impact of these delays, then substntiate your E.O.T claime based on ur approved program.

Regards,
Dayanidhi Dhandapany
User offline. Last seen 3 years 11 weeks ago. Offline
Joined: 18 Mar 2003
Posts: 470
Groups: None
you have to check with your contract agreement for the method of delay analysis part. Also you can use your approved baseline programme developed in P3 to show the slippage of activities on the critical path and if it is caused by owner’s delay events, then you can claim for EOT as per your contract agreement. (use your current updated schedule in p3 and keep target schedule as the approved baseline programme)

HTH