Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Punchlist Items

20 replies [Last post]
Christian Adrian ...
User offline. Last seen 6 years 5 weeks ago. Offline
Joined: 3 Jun 2003
Posts: 193
Groups: None
Dear Fellows

I would like to hear different views on this matter.

scenario:

1. The contractor has submitted a remaining works programme to the ER.
2. ER reviewed the programme and replied with comments.
3. Contractor responded the ER’s comments accordingly.
4. ER replied and requested for a complete programme for the remaining works saying it should include their punchlist items.

My question would be, is it necessary to include this items in the programme?

Appreciating your views in advance.

Christian

Replies

Clive Randall
User offline. Last seen 17 years 37 weeks ago. Offline
Joined: 15 Aug 2005
Posts: 744
Groups: None
I dont know about petro chem but in building we will start punching out as trades complete floors, that way we dont have work over defective work and have a small close out defects list
Clive
Norzul Ibrahim
User offline. Last seen 17 years 46 weeks ago. Offline
Joined: 17 Dec 2005
Posts: 165
20% just example...but i think still possible
Raja Izat Raja Ib...
User offline. Last seen 14 years 14 weeks ago. Offline
Joined: 2 Jun 2005
Posts: 299
Hi,
If I not mistaken, Punchlist will be count after first submit handover with mechanical catalogue / manual of the work area, If not it will call "remaining work checklist". Correct me if wrong.

regards
Clive Randall
User offline. Last seen 17 years 37 weeks ago. Offline
Joined: 15 Aug 2005
Posts: 744
Groups: None
Norzul
Do you ever get 20% rework thats astonishing
Clive
Raja Izat Raja Ib...
User offline. Last seen 14 years 14 weeks ago. Offline
Joined: 2 Jun 2005
Posts: 299
Hi Norzul,
Yes, MCD is Mechanical Completion Date, not "Man Compete Donkey" who is Cleverest,I hope not miss interpret.


Norzul Ibrahim
User offline. Last seen 17 years 46 weeks ago. Offline
Joined: 17 Dec 2005
Posts: 165
Puchlist is rework or PONC as we call it in our company. For planning purpose I think we should consider amount of rework to be done when we prepare the overall schedule, maybe 5%, 10%, 15%, or 20% of the duration. The % depends on the experience....
Norzul Ibrahim
User offline. Last seen 17 years 46 weeks ago. Offline
Joined: 17 Dec 2005
Posts: 165
Raja,

What is MCD...mechanical completion date?
Philip Jonker
User offline. Last seen 16 years 39 weeks ago. Offline
Joined: 7 Nov 2004
Posts: 852
Groups: None
Hi Clive,

Agreed, however the time, that I include is nominal, based on the intricacy of the job, the quality standards, etc. The problem happens when you receive the punchlists, you can then make a accurate assessment of the time required to correct these items. The first step, is to categorise the items, and we normally use three catgories:
Cat 1: Items that affect safety and Operation, omitted and not per as the design.
Cat 2: Items of concern in safety and operation, but not included in the design.
Cat 3: Items, which is aesthetic, etc.

The point is that you can hand over portions of the job to commissioning, without Cat 3 items being completed, Cat 2 items is items, where decisions need to be made, as to whether they affect commisioning, and are normally split up between cat 1 and 3 as decisions are made. Cat ! are therefore the items to be concetrated on, and cat 2 should be included as seperate activities in the program.
I find the best way to to run this is with a punchlist, with dates, and monitor it on a frequent basis, anything from daily, hourly or weekly meetings, dependant on the urgency of the project.

Regards
James Griffiths
User offline. Last seen 16 years 34 weeks ago. Offline
Joined: 19 May 2006
Posts: 435
Groups: None
Nicely put, Clive.

James.
Clive Randall
User offline. Last seen 17 years 37 weeks ago. Offline
Joined: 15 Aug 2005
Posts: 744
Groups: None
Its an interesting point
No not who the ER is or even what a punchlist is as that is the semantics.
Do you include for punch lists (snagging) or not on the programme. I will usually include some time for this on the master programme as even the best contractors will have to rework some items. However many snagging items can be carried out after practical completion ie when the building or facility has achived fit for purpose condition.
It would not be unreasonable therefore to place items in the maintenance period after practical completion or contract completion.
James has a good point what does the contract require you to do and does or will the engineer really understand a very detailed snagging programme.
Often it is better to have a completely different arrangement for punch list items which can be tracked under a data base rather than a programme, this is mainly due to the logic constraints ie fixing 700 locks can run concurrently resources witstanding.
Clive
Raja Izat Raja Ib...
User offline. Last seen 14 years 14 weeks ago. Offline
Joined: 2 Jun 2005
Posts: 299
Hi Christ,
actually i have doubt what u say "My question would be, is it necessary to include this items in the programme?".
Actually Punchlist is remaining work which in progress to be done before MCD. My qestion here:
1. What will happen if u include the items, is it will be count your resources twice(mahours, budget)and double job for your scheduling.

Feel uncomfortable not to tell about this. until cannot sleep.

regards
James Griffiths
User offline. Last seen 16 years 34 weeks ago. Offline
Joined: 19 May 2006
Posts: 435
Groups: None

Christian: Thankyou.

Philip,

Now that you have a clarification, do you have a view?

James.
Philip Jonker
User offline. Last seen 16 years 39 weeks ago. Offline
Joined: 7 Nov 2004
Posts: 852
Groups: None
Hi Christian,

Hopefully in future, you will clarify these things in your first posting, to prevent confusion. Thanks for your reply and clarification.

Regards

Philip
Christian Adrian ...
User offline. Last seen 6 years 5 weeks ago. Offline
Joined: 3 Jun 2003
Posts: 193
Groups: None
Hi Fellows

For clarity ER stands for Employer’s Representative in my post, in others it could be another meaning depending on the definition stated in the contract, but James you got the question right and thanks for your view.


Cheers

Christian
Philip Jonker
User offline. Last seen 16 years 39 weeks ago. Offline
Joined: 7 Nov 2004
Posts: 852
Groups: None
Hi James,

I was not insulting you, but admit you were not sure what the question was. Iwas giving advice, clarify what the person was talking about. Your answer may have been right, or if not, a total waste of time, and time is supposed to mean something to us planners.

Regards

Philip
James Griffiths
User offline. Last seen 16 years 34 weeks ago. Offline
Joined: 19 May 2006
Posts: 435
Groups: None
Ha, ravin’ ha, Rajat, :-)

It could also mean "Engineering" or "Executive". Regardless, the principle of Christian’s question is the same. If ER is higher-up than you (the Contractor) in the food-chain, then ER can be considered your "client". The principle under-pinning my response remains.


James.
Raja Izat Raja Ib...
User offline. Last seen 14 years 14 weeks ago. Offline
Joined: 2 Jun 2005
Posts: 299
Hi,
If i not mistaken ER means Estimator or to much influence watching "Emergency Room" series. He he he...
James Griffiths
User offline. Last seen 16 years 34 weeks ago. Offline
Joined: 19 May 2006
Posts: 435
Groups: None
Philip,

Thankyou for the insult. If, however, you care to read the question, it states that the “contractor has submitted…..should include punch-list.” By most interpretations, the contractor and punch-list author is the team/company that works at the coalface, actually doing the work. Therefore, any “submission” of programmes is more than likely to be upwards in the hierarchical chain of authority, becoming ever-more summarised in the process. It is not really relevant as to precisely who ER is; only that ER is “upwards” in authority relative to the contractor. Using this assumption, Christian’s question was perfectly clear. However, I’m sure that he will clarify any misconceptions on my part.

Over to you, Christian.

James
Philip Jonker
User offline. Last seen 16 years 39 weeks ago. Offline
Joined: 7 Nov 2004
Posts: 852
Groups: None
Hi guys,

I have this problem, the designers, produce a program, and under the headings Earthwork Lateral Support and Full design Packege, they used the following two abbreviations, ELS and FDP, they used these in their activity descriptions, I imported their programmes, and upon review, their questions was what the abbreviations meant. It was very obvious, just by looking at their WBS, but they could not figure this out. I have started a schedule abbreviations dictionary to assist people like designers to remember their own handiwork. We had to create a wbs for monthly payment milestones, and the logical coding was PMS, imagine the hilarity which followed this one as these are updated once a month, and is very painful.

My suggestion is to Christian, explain what you are talking about, and James do not answer questions you do not understand.

Regards

Philip
James Griffiths
User offline. Last seen 16 years 34 weeks ago. Offline
Joined: 19 May 2006
Posts: 435
Groups: None
Christian,

The validity of the ER’s request really depends on:

1) At what stage of the project you’re at.
2) At what level of detail the “contract programme” resides.
3) Why the ER is asking for such detail.
4) What the contract itself states

Your ER (what does ER stand for?) is probably concerned that the scope of remaining work isn’t particularly well-defined; thus he is asking you to portray your understanding of such work by asking you to provide the punch-lists. Anybody can compile a comparatively high-level programme that looks good but may not be substantiated by the nitty-gritty detail that punch-lists provide. However, I wouldn’t expect that level of detail to reside on a programme….it would be unmanageable.

We have just come through a very similar situation, where our client asked for our detailed programme. The contract programme has about 150 lines and the client seemed to be worried that we didn’t quite have an understanding of what we were doing. In order to “help us” and “offer advice”, he wanted to see what plans we were working to. I explained that he really ought not to ask for this because it contains over 4000 lines and, in the format that he wants it, he would have absolutely no hope of assimilating the data. However, we provided it; he looked at it, said nothing and just carried-on. I can only assume that he was satisfied that we actually had a plan. Of course, we stated that just because it is on the plan, it doesn’t necessarily mean that we will work in exactly the sequence shown; therefore, he (the client) must not attempt to monitor us against such detail.

Ultimately the important thing was that we showed him our plan, walked him through our progress-reporting analysis and showed him our monthly “milestone” punch-list process. This gave him the knowledge and confidence that we did have a process and we knew what we were doing…..it was just that it was taking too bloody long to do it!

HTH.

James.