NEWS - One or two users are experiencing intermittent problems with Internet Explorer Version 10, if you have problems entering data, for now, please try a different browser. Sorry :(

Provisional and Prime Cost Items

6 replies [Last post]
Mohammed Irfan Sh...
User offline. Last seen 14 weeks 1 day ago. Offline
Joined: 10 Jul 2005
Points: 44
Hi Friends,

1. Can we accept a Provisinal Sum Item nominated by the engineer as a Unit Rate Item?

2. Whats the difference between the P.C. for Supply & Fix and P.S. except for Builders work cost?

Sort me out friends.

Replies

Vishwas B PMP PSP...
User offline. Last seen 34 weeks 6 days ago. Offline
Joined: 24 Apr 2004
Points: 95
Hi Stuart,

Long time...... Wassup at your end?

The 15% in question is laid down or defined in the contract. If the PS or PC-Rate amount varies +/- 15%, then the Main Contractor has the right to revise his attendance / overheads & profit. But, if the variation falls in the 15%-range, then there shall be no change in the percentage of attendance / overheads & profit over the PS/PC-Rate item.

Cheers

Vishwas
Stuart Ness
User offline. Last seen 1 year 23 weeks ago. Offline
Joined: 30 Jun 2004
Points: 352
Groups: None
Irfan,
To return to your original question, a “Provisional Sum” is a sum that is provided for work or for costs that cannot be entirely foreseen, defined or detailed at the time of issuing the tender documents. In addition, during the administration of the Contract, Provisional Sums are spent by the Contractor after the exact nature and extent of the Work have been agreed.
It appears that in your situation, you simply have a Provisional Rate Item, which can be firmed up once the nature and extent of Work have been ascertained.
I would suggest that you avoid accepting a “Provisional Sum” (which is flexible and subject to change) as a Unit Rate Item until such time as you are sure of the nature and extent of the work in question.


A “Prime Cost Sum” means a sum provided for work or services to be executed by a nominated sub-contractor or for materials or goods to be obtained from a nominated supplier. In addition the Prime Cost Sum will be subject to an uplift for the Contractor’s attendance and profit. These uplifts are generally not applicable to Provisional Sums.

Hope this helps,

Stuart

www.rosmartin.com
Mohammed Irfan Sh...
User offline. Last seen 14 weeks 1 day ago. Offline
Joined: 10 Jul 2005
Points: 44
Hi Stuart
Hi Vishwas,

Well that got my eyebrows up too. I think he means about the total contract value.

Irfan
Stuart Ness
User offline. Last seen 1 year 23 weeks ago. Offline
Joined: 30 Jun 2004
Points: 352
Groups: None
Vishwas,

Where do you get this +/- 15% from?



Stuart

www.rosmartin.com
Mohammed Irfan Sh...
User offline. Last seen 14 weeks 1 day ago. Offline
Joined: 10 Jul 2005
Points: 44
Hi Vishwas,

Nice to hear from you,

As per our BOQ, some of the items are P.C. for Supply & Fix and the nomination has been done like wise.
Well, presuming the item is P.C., the conditions of Facilities to be provided by the main contractor for crainage and Site Offices,etc. for each P.S. Item as per general provisions is not applicable.
Well does this prove a point.

Waiting for your comment, Habibi.

Irfan
Vishwas B PMP PSP...
User offline. Last seen 34 weeks 6 days ago. Offline
Joined: 24 Apr 2004
Points: 95
1. Yes. You can. The client has the right to re-contract the PS-Items to the Main Contractor in any way he/she wants but the total amount should not vary beyond +/- 15% of the PS-Item Cost.

2. "PC" stands for "Prime Cost". That means, the rate given is for the Material only. Supply & Fix is the Main Contractor’s responsibility, and, he has to add for supply & fix to the PC-Rate.

Cheers

Vishwas

Market Place

The toolkit provides advanced analytical tools which can help identify areas of poor schedule quality at the click of a button.
Books and training material available from an internationally recognised publisher and PMI accredited REP. Teach yourself or run your own in-house or public planning courses.
EVA18 is the major UK event for Project Control knowledge, know-how and networking. EVA is a conference organised by a project management practitioner for project practitioners and stakeholders
A comprehensive product suite with the flexibility to meet the varying needs of everyone involved in running projects
We want to build software that solves real problems, allow people to work more productive and happier.