Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Provisional Sum

7 replies [Last post]
Razi Khan
User offline. Last seen 7 years 31 weeks ago. Offline
Joined: 17 Jun 2004
Posts: 74
Groups: None
Hi Planners and Contracts People

Please guide me in the following matters:

1. When instruction to execute the work for partial or whole sum of amount for "Provisional Item" to contractor then what will be the contractual position of Contractor regarding Extension of Time ?

2. If a certain amount against a work is neither the part of "Original Contact Amount" nor the part of "Provisional Sum" but included in Contract Documents as "Declaration" than is that amount can be called as "Provisional" although strictly speaking it is not mentioned as such.

Replies

Joe Mansour
User offline. Last seen 3 years 8 weeks ago. Offline
Joined: 10 Sep 2002
Posts: 46
Groups: None
May I add that when the Engineer makes a decision regarding the provsional sum, two questions must be considered: What and when.
For the What, was the provsional sum defined or undefined (according to SMM7 definition)? If it was undefined, or if the scope of nominated subcontractor has increased from the original given scope, there is a possibility of obtaining extension of time (and a variation). If not the chance is less.
For the When, I usually include in all my schedules milestones for the Engineer to make decisions regarding each provisional sum. These milestones would be logically linked to the relative activity. The duration of that activity would be estimated based on the contract documents concerning the provisional sum, or otherwise based on the best guess.

Another case to share that might be of interest to somebody. We are currently building a hospital. The original BOQ included a provisional sum of 8M USD for medical equipment and furniture. The Engineer has nominated 17 medical equipment contractors for that provsional sum, instead of one. I submitted a claim and won it (with difficulty) for extra time and cost on the basis of seggregating the provisional sum into multiple contracts which we (the Contractor) had to deal with each one of them, instead of dealing with one. (the contract is a FIDIC 87/92).

Joe
Andrew Ng
User offline. Last seen 4 years 36 weeks ago. Offline
Joined: 3 Jul 2004
Posts: 52
Groups: None
For sake of clarity, I must confess that my experience with JCT and FIDIC were the earlier versions and my comments sated in the last posting as such may no longer be tenable in the light of the recent amendment made thereto.

It was in fact my finding from participants on a conference on contracts and delays last week that what Stuart stated re the provisions in SMM7 was correct. It is also possible that what he said in relation to the JCT edition is equally applicable in the latest edition of the FIDIC which I have not come across nor checked.

I would be most pleased if Stuart or others wish to take this on and elbaorate their current understanding of the same.
Stuart Ness
User offline. Last seen 12 years 15 weeks ago. Offline
Joined: 30 Jun 2004
Posts: 352
Groups: None
Hi Razi,

I would suggest that you may have a fair right to claim EOT where the Engineer/Architect issues an instruction as to how and when Provisional Sums should be spent. A Provisional Sum is simply a bag of money allowed for carrying out a part of the Works, without any indication of the workscope, quantities or time involved.

Under JCT80 Form of Contract, Provisional Sums are under the same Clause heading as Variations (Clause 13). Under Clause 25.3 of JCT80, the Contractor is entitled to an EOT as a result of a Relevant Event, which by definition under Sub-Clause 25.4, includes dealing with an Architect’s instruction under Sub-Clauses 13.2 and 13.3. Sub-Clause 13.3 addresses the expenditure of Provisional Sums.

Following this concept, Razi, I suggest that you look at your EOT Clause, and it should allow you to have an EOT as a result of implementing instructions issued by the Client/Engineer/Architect. Work is ear-marked “Provisional” simply because the Client doesn’t know precisely what he wants to have done – sometimes he doesn’t even have a Specification to relate to. Consequently, he wants to make a financial provision in the Contract Price to ensure that there is enough money in the budget for the particular item, but normally he fails to include a time provision for the item (usually in the hope that the Contractor will offer to consume his own float in carrying out this additional work.)

There is a school of thought that considers that it is appropriate for the Contractor to have already made some allowance in his programme for executing “Provisional Items”, but this is dependant upon the Provisional Sum being “defined”. SMM7, for example, makes reference to “defined” and “undefined” Provisional Sums, and defined Provisional Sums are deemed to have their programming requirements already included in the Contract Schedule. Execution of an undefined Provisional Sum will allow an EOT to be claimed.

If you do not have such clarification as SMM7 in your Contract, then I am afraid that we may be back to the “how long is a piece of string?” argument! My advice would be that if the extent of additional work arising from a Provisional Sum is substantial, then the Contractor should be entitled to an EOT even where the Provisional Sum is not exceeded, since there would be no other criteria in the Contract documentation for the Contractor to gauge the nature and extent of work that was to be carried out, and he is, after all, carrying out a formal instruction.

The crux of the matter, however, really also relates to WHEN the instruction in regard to the Provisional Sum was issued. It may be impossible to carry out the additional work without it impacting the CP, due to the specialist nature of the work, or long lead times etc.. In such a case I would certainly pursue the right to claim an EOT.

With regard to your second point about “Declaration”, I have come across this a few times in regard to “Options”, in which the Client has the option to have a part of the Works increased (or decreased) during the engineering phase for technical reasons. These “options” which the Client may or may not use normally have a “sell-by” date; in other words, the Client only has a limited time in which he can exercise the options on offer. If he does take up the option before the “sell-by” date, then usually the Contractor is not entitled to an EOT, but if the Client calls for the option at a later date, then the Contractor is usually entitled to an EOT.

I hope this helps.

Cheers,
Stuart
Razi Khan
User offline. Last seen 7 years 31 weeks ago. Offline
Joined: 17 Jun 2004
Posts: 74
Groups: None
Thanks Andrew for your precise interpration and thanks to Shazad also for further reinforcing your response.
Andrew Ng
User offline. Last seen 4 years 36 weeks ago. Offline
Joined: 3 Jul 2004
Posts: 52
Groups: None
That’s what I said essentially, no claim unless under exceptionally onerous circumstances...
Shahzad Munawar
User offline. Last seen 8 years 51 weeks ago. Offline
Joined: 2 Jul 2003
Posts: 551
Groups: None
You cannot claim any Extension of Time on the basis of Provisional Sum.Provisional sum is entirely different from time related costs.
Andrew Ng
User offline. Last seen 4 years 36 weeks ago. Offline
Joined: 3 Jul 2004
Posts: 52
Groups: None
Dear Razi,

a) as a general rule so far as my past experience with JCT and FIDIC (Redbook) type clauses, there is no possiblity of you claiming for any time extension on the basis of partial or whole expenditure of the Prov Sum. Of course if the scope described or sum provided can be proven as grossly under provided, and the additional time required for the increased scope can be proven to have impacted or overextended any activities on the critical path, I reckon that a fair Contract Administrator would not disregard any well presented application.

b) I have not come across any such "declaration" in the past, but if they possess the common attributes of provisional or prime cost(PC) sums for which the scope and value of each declaration are described in sufficient details and accuracy, and for which the contractor is reimbursed a percentage of the sum/s as his "profits and attendance", I am inclined to guess that the EOT entitlement would as per case a) above.