Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Provisional Sum v/s Variation Order

3 replies [Last post]
Pradeep Mendonca
User offline. Last seen 15 years 38 weeks ago. Offline
Joined: 28 Jul 2007
Posts: 15
Groups: None
Hi all !!

Just joined in and found to be a great discussion forum.

I have one question:
The engineer got the quotations from other nominated sub contractors for provisional sum and found to be extremely high as against the amount stated in contract PS. So, the engineer instructed the main contractor to carry out certain works of provisional sum based on the BOQ rates referring to clause 58.2 & 52 of FIDIC 1987. Any works where there is no rates stated in BOQ is to be analysed and agreed.

Does the contractor has any rights to object to carry out such works as these works were priced way back (say 2 years). Also, the contractor would have adjusted his price in BOQ while tendering. For this particular item, the unit rates are much lower compared to the present market prices.

Guys, please advice.
Thanking you all in advance.

Pradeep

Replies

Bolisetti Jogiraju
User offline. Last seen 5 years 2 weeks ago. Offline
Joined: 7 Jul 2007
Posts: 32
Groups: None
Pradeep !
You are absolutely right.
You have to substantiate with invoices/vouchers etc added up with your OH&P.

Cheers
Pradeep Mendonca
User offline. Last seen 15 years 38 weeks ago. Offline
Joined: 28 Jul 2007
Posts: 15
Groups: None
Thanx Jogi...

If we read clause 58.2, the PS is instructed by engineer to contractor (a), AND nominated sub contractor (b).

That means...the contractor will coordinate the works ONLY and will be paid as per 59.4. FIDIC doesnt mention that PS has to be carried out by contractor ALONE.

So the engineer cannot instruct the contractor to do PS based on BOQ rates and hence a separate nominated sub contractor has to be appointed where the contractor takes his overheads and profit.

Am I right on these lines??
Bolisetti Jogiraju
User offline. Last seen 5 years 2 weeks ago. Offline
Joined: 7 Jul 2007
Posts: 32
Groups: None
Hi
Pradeep !
Contractor can not object to carry out works which are:

expressly required to complete the said project
affected by price escalation,unless Clause related to "Changes in Cost and Legislation" exists in Contract.

Hope,you got it.

Cheers