User defined columns

1 reply [Last post]
Chris Wilson
User offline. Last seen 1 week 2 days ago. Offline
Joined: 21 Oct 2016
Posts: 18
Groups: None

Hi,

Does anyone know if its possible to create user defined columns that you can populate from drop down lists?

looking to create  a columns where I can have units such as kg, tonne, m , m2 etc

Regards

Chris

Replies

Ben Taunt
User offline. Last seen 4 days 11 hours ago. Offline
Joined: 16 Jan 2012
Posts: 102
Groups: None

Hi Chris,

You could do this simply using Code Libraries.  Create a Code Library for your units, and then set that as a single select option.  Add the Code Library as a column and a drop down with your options will appear...

Also means you can then easily filter and sort etc.

Ben @ Powerproject