Consumable Resources - Reports

No replies
Euan Rennie
User offline. Last seen 10 weeks 2 days ago. Offline
Joined: 26 Feb 2018
Posts: 4
Groups: None

I have my programme fully resourced with "Consumable Resources" i.e Materials.  

I would ideally like to be able to export a spreadsheet which shows me:

  1. The quantity I have of each Consumable Resource 
  2. The % of the Consumable Resource which has been used to date based on Programme progress

Is there anyway to do this?  I can see the quantity of each Consumable Resource by going into Libary Explorer > Consumable Resources and selecting "Show All Fields."  Is there a way to export what I can see here into a spreadsheet?

I'm not sure if the software can do what I'm asking for above however it seems like something it should be able to do.  Any help would be greatly appreciated.