Scheduled Resource Reports

1 reply [Last post]
Chris Lothian
User offline. Last seen 1 year 46 weeks ago. Offline
Joined: 18 May 2007
Posts: 34

Hi All,

I am trying to set up a tabular report in excel so that others who cannot use Asta can view resource levels. I have used MS Project, and would very much like a table similar to that of either the Resource Sheet or Resource Usage views that are available as default in MS Project.

I need the resource name to be listed down the left column, with its daily/weekly/monthly or total assignment in a column to its right.

 

Thanks

 

Chris

Replies

Mike Testro
User offline. Last seen 27 weeks 6 days ago. Offline
Joined: 14 Dec 2005
Posts: 4420

Hi Chris

The easiest way is to set up the required columns in the left hand PowerProject spreadsheet and just copy /paste directly to excell.

Alternatively you can set up a resource Histogram view and export data directly to excell.

Finally within Asta Powerproject there is a powerful report writer that will export data directly to Excell - but that is a bit messy.

Best regards

Mike Testro