Import file

3 replies [Last post]
Andy Hudson
User offline. Last seen 2 years 46 weeks ago. Offline
Joined: 18 Oct 2016
Posts: 33
Groups: None

Hi Mike,

I am trying to save file as XER to import it to P6 but got the attached error/warnings.

http://imgur.com/a/E27kh

Please advise me the steps to follow so I can save file as Full as it is without the above warnings and import the whole programme into P6 with same headings and subheadings as in Asta without any error.

Cheers

Replies

Sterling Gallagher
User offline. Last seen 8 weeks 5 days ago. Offline
Joined: 4 Oct 2019
Posts: 12
Groups: None

Hi Mike

Slight variation to this question, I receive files from Asta Power Project saved as an XER file which will import to the Standalone Desktop P6 (SQL lite), but fail when importing to the SQL Network databases.

 

Is there a specific method for Asta users to creat an XER file and have you encountered the issue before?

Andy Hudson
User offline. Last seen 2 years 46 weeks ago. Offline
Joined: 18 Oct 2016
Posts: 33
Groups: None
Thanks mike.
Mike Testro
User offline. Last seen 4 weeks 2 days ago. Offline
Joined: 14 Dec 2005
Posts: 4403

Hi Andy

Use File>Safe As>primavera .xer

Job done.

Best regards

Mike Testro