Filtering by Trades Contractor

3 replies [Last post]
Dominic Planner
User offline. Last seen 1 year 31 weeks ago. Offline
Joined: 7 Jun 2017
Posts: 22
Groups: None

Hi All, 

Is it possibel to filter by trades contractor? I am currently using version 13.0.02.069 of Asta

 

Thanks

Replies

Dominic Planner
User offline. Last seen 1 year 31 weeks ago. Offline
Joined: 7 Jun 2017
Posts: 22
Groups: None

Spot on, thank you gents

Mike Testro
User offline. Last seen 27 weeks 2 days ago. Offline
Joined: 14 Dec 2005
Posts: 4420

Hi Dominic

You can also filter on the task title by typing *laster* which will then pick up Plasterer - Plastering etc with or without capitals.

You can then add a code to the filter if you wish.

Best regards

Mike T.

Ben Taunt
User offline. Last seen 1 year 26 weeks ago. Offline
Joined: 16 Jan 2012
Posts: 113
Groups: None

Hi Dominic,

If you set up your project using the default template, you may already have the filter setup for this.  Go to View > Filter > Codes > Which Code? [asks for a code(s)].  You can then chose the trades contractor code library from the list.

If you used a different template without the filters pre-installed, you'll need to create the filter from scratch by going View > Filter > New... and following the wizard.  Check the Help File for more details or contact your local Asta Powerproject support team.  You can then save that as a default filter for a certain view etc.

In v14.0.02 we may filtering by code library even easier - you can now just double-click the name of the code in the project viewer to enable a code library filter of the tasks in the current view(called a Code Breakdown Structure).  This mirrors the functionality we've had for Resource Breakdown Structures since v12.

Hope that helps,

Ben @ Asta Powerproject