Filtering on Predecessors and Successors

2 replies [Last post]
Oliver Johnstone
User offline. Last seen 14 years 37 weeks ago. Offline
Joined: 13 Mar 2006
Posts: 5
Groups: None
Can anyone tell me how to create a filter which will present the direct predecessors and the direct successors to a particular activity.

Thanks

Replies

Carlos Arana
User offline. Last seen 7 years 3 weeks ago. Offline
Joined: 6 Jun 2009
Posts: 178
When inside this P&S view, what’s the quickest way to jump to the pred/suc of one of those activities in the view?
Mal Leadbetter
User offline. Last seen 12 years 3 weeks ago. Offline
Joined: 22 Aug 2001
Posts: 61
Groups: TILOS
Oliver

From an unfiltered view, click on the activity whose predecessors / successors you wish to see.

Then go to toolbar, select view. From the drop down menu select view and from the next drop doown menu you should see an option for Predecessors & Successors. Click this and this gives you your direct predecessors and successors

Knowing (or not as the case maybe) PowerProject, there is probably a shortcut to do the above!

Hope this helps

Mal