Critical Links

3 replies [Last post]
Craig Adams
User offline. Last seen 13 years 44 weeks ago. Offline
Joined: 11 Oct 2006
Posts: 71

Hello Fellow Planners,

Trying to change the thickness of critical links so they are more visible - only seem to be able to change color.

Anyone know how to change thickness?

Thank you in anticipation,

Craig Adams

Replies

Mike Testro
User offline. Last seen 42 weeks 2 hours ago. Offline
Joined: 14 Dec 2005
Posts: 4420

Hi Craig

You are right - can only change colours and names on pre set links.

One for Andrew Willard for version 11-3

Best regards

Mike Testro

Craig Adams
User offline. Last seen 13 years 44 weeks ago. Offline
Joined: 11 Oct 2006
Posts: 71

Hello Mike,

I've been in this section and can change various aspects of all links however, with the critical links I only have the option to change the colour.

Cheers,

Craig Adams

Mike Testro
User offline. Last seen 42 weeks 2 hours ago. Offline
Joined: 14 Dec 2005
Posts: 4420

Hi Craig

In the library explorer links dialogue there is a section where you can change colour - style and thickness of all links and add any number of new categories.

I use resource levelling links that can be switched on and of in the Options Reschedule dialogue.

Best regards

Mike Testro